The construction of our new police department headquarters is well under way and the General Contractor and all of the trades are making great progress in a well-coordinated effort to complete the project in 2024.

LATEST UPDATE:
(as of April 30, 2024)

  • Framing & roofing: 100% complete

  • Plumbing: rough-in 95% complete

  • Electrical: rough-in 95% complete

  • Insulation: 98% complete

  • HVAC: 95% complete

  • Drywall: 98% complete

  • Ceilings: 0% complete

  • Exterior & parking lot: 60% complete

  • Tele-data wiring: 90% - starting 3/25

  • Access control: 25% - starting 3/25

  • Surveillance: 25% - starting 3/25

  • Utility hookups: 30% (water, sewage, electric, gas)

  • Roof screening to be installed in late Spring to hide the exterior duct work

  • The project is slated for substantial completion by early Summer 2024.
     