NEW MALVERNE POLICE HEADQUARTERS
1 ARLINGTON AVENUE, MALVERNE
The construction of our new police department headquarters is well under way and the General Contractor and all of the trades are making great progress in a well-coordinated effort to complete the project in 2024.
LATEST UPDATE:
(as of April 30, 2024)
-
Framing & roofing: 100% complete
-
Plumbing: rough-in 95% complete
-
Electrical: rough-in 95% complete
-
Insulation: 98% complete
-
HVAC: 95% complete
-
Drywall: 98% complete
-
Ceilings: 0% complete
-
Exterior & parking lot: 60% complete
-
Tele-data wiring: 90% - starting 3/25
-
Access control: 25% - starting 3/25
-
Surveillance: 25% - starting 3/25
-
Utility hookups: 30% (water, sewage, electric, gas)
-
Roof screening to be installed in late Spring to hide the exterior duct work
-
The project is slated for substantial completion by early Summer 2024.
-
New Police Station